초록 close

In the construction of high-rise buildings, form work is the largest single cost component of a concrete structural frame and the critical trade when it comes to setting construction speed. A shortage of skill workers and increased labour costs also increases the demand for new form work systems. Therefore, the purpose of this study is to propose a new unit table form system that enables concrete structural frame work to be executed in safe condition, while still providing significant savings in the overall project schedule and cost. The results of being applied proposed unit table form to high-rise residential building construction are as follows;(1) The cycle time of form work system was 4 days at a typical floor of high-rise building. (2) The labour cost of form work was reduced by 20%, and (3) The safety of concrete structural frame works was improved.