초록 close

A case study to reduce maintenance time using PERT in Steel Making Plant is introduced. By redefining maintenance activities and rearranging maintenance jobs in accordance with maintenance priorities and precedence constraints, current maintenance time, 13 days, has been reduced to 10 days. Due to the increased production time in steel making plant through this study, production increase of molten steel is expected.